Generic Zerista Project Plan

This outlines the basic plan our Project Managers will walk you through. This timeline ensures we will have enough time to train you to use your Zerista app to it's fullest potential.

This timeline will be customized to you based on time constraints and additional features you may add.

  Zerista 12 week Project plan
   
12 Weeks Out (3 months prior to event date) Client is provided link from Zerista Account Manager to access the site admin.  Client will add event details and graphics by working through Start-up tabs, followed by other Launch Pad tasks.  
   
11 Weeks Out Client and Zerista Project Manager kickoff project, review graphics, theme and move forward with app submission. Site permissions.
10 Weeks Out Client continues to work on Launch Pad tasks, gathers data or provides integration contact details.
   
  Integration team confirms access
   
  Training/tech call 1 - review basics of navigating admin and front end, data templates, sponsorships, gaming overview, add-on features (leads, surveys, polling, white-label).  Onsite marketing materials
   
8 Weeks Out  Integration team update
   
7 Weeks Out Training/tech call 2 - review exhibitor process, troubleshooting data in the system, custom pages,  testing of the site, linking social, review invite templates and process, broadcast messages
   
6 Weeks Out Client adds final data to site, proofs information, finalizes game set-up.  If there is an integration target integration completion date update.
   
5 Weeks Out

Training/tech call 3 - Review Site - are exhibitors linked to companies, gaming set-up and testing, testing feedback, app and desktop navigation.

   
4 Weeks Out

Integration Complete

   
3 Weeks Out

Client invites internal users to site for feedback/review (eg staff)

   
 

Client provides feedback in writing to Project Manager to review on final call.

Final Tech Call - Review onsite admin functions and onboarding, review broadcast message functionality, surveys, gaming/leaderboard questions

   
2 Week Out 

Client invites users to site.  Project Manager will provide insight on target launch date on kickoff call, but our typical target launch is 2 weeks prior to event date.

   
1 Week Out

Client sends email reminders

   
Event

Don’t forget to think ahead! How are you promoting the app at the event?  Where do they go for support?

 